About: vlm

Profile

Author Archives: vlm


New Rooftop Package at Independent Record Pressing

New Rooftop Package at Independent Record Pressing

A.M. Botte was contracted for an entire HVAC design build project at Independent Record Pressing in Bordentown, New Jersey. We provided a total turnkey mechanical job for our customer. The project included (8) 12.5 ton York rooftop package units. A.M. Botte performed all structural steel work for the new equipment, including roof openings and roof flashing. On the inside of the building we installed all new exposed spiral duct work with enlarged diffusers. On the outside of the building we installed a new, 200 ton, York air cold water chiller on a new 6 inch concrete housekeeping pad. We fabricated all new 6 inch welded steel pipe for the new chiller with custom pump assemblies. Our team also included all needed line voltage power to complete this project. The facilities manager Sal was very pleased with all the work performed and has since awarded A.M. Botte the maintenance agreement on for the entire building.

Emergency HVAC Replacement for Woodcrest Country Club

Emergency HVAC Replacement for Woodcrest Country Club

We were called to an emergency service (outage) call at Woodcrest Country Club, where we found that two of the main package HVAC units had failed. Due to the severity of the call, we sent our General Manager and Service Manager to make emergency repairs and keep the units running while a replacement could be designed. Our team was able to order, and build to custom specifications, two new 30 ton and 40 ton York gas electric package units. These units took approximately 16 weeks to be built, so we tasked our service department with keeping the old units running the best they could during this busy time for Woodcrest Country Club. Once the new units arrived, we executed our detailed plan for their replacement. We worked to schedule around multiple events our client had, and selected a strategic day for the work to be completed. Utilizing a 125 ton Crane, and a large group of manpower, we were able to complete this replacement in one day with no disruption to the customer.

WATCH – Emergency HVAC Replacement for Woodcrest Country Club

HVAC Package for Tonewood Brewery in Barrington, NJ

HVAC Package for Tonewood Brewery in Barrington, NJ

A.M. Botte recently completed an entire HVAC system installation at Tonewood Brewery in Barrington, NJ. We were hired by Eli Facchinei, who is the owner/operator to design build and install all new HVAC for his new  brewery location in Barrington, NJ. We installed (2) York 15 ton RTU’s with exposed duct work on the roof. The duct work then dropped down and transitioned into double wall custom oval/round spiral. We installed (2) Macroaire 10’ diameter fans along with (1) 14’ diameter fan, these units where installed over top of the vats to assist in cooling the space. We installed (4) high efficiency Reznor unit heaters in the brewing area. We also installed a York mini split to provide heating and cooling in the lab. With craftsmanship and attention to detail our team was able to design build and install all of the HVAC on time and in budget. Craftsmanship that will last a lifetime! 

Highlights of HVAC Package for Tonewood Brewery in Barrington, NJ

  • Complete System and Ductwork Design
  • 2 York 15 Ton Units
  • 2 Macroaire 10’ diameter fans
  • 1 14’ diameter fan
  • 4 high efficiency Reznor heaters
  • 1 York mini split system

“The oval duct was a great idea we love it!”
– Eli Facchinei: Owner, Tonewood Brewery

Photos of HVAC Package for Tonewood Brewery in Barrington, NJ

10 Ton Rooftop Unit in Philadelphia for Flynn Property Management

10 Ton Rooftop Unit in Philadelphia for Flynn Property Management

We recently installed a 10 ton rooftop unit in Philadelphia for Flynn Commercial Property Management. Our team got into and out of Philadelphia before the traffic rush and got this valued commercial customer up and running without downtime. Anytime we are called to do work in the city, we make sure our cranes are on-site well ahead of the morning traffic rush and out of the city before noon. This customer saw absolutely no disruption to their daily routine and our installation likely went unnoticed by their tenants.  

Highlights of this 10 ton rooftop unit in Philadelphia

• The unit that we installed over 15 years ago was due for replacement
• The work was scheduled at 5am start to avoid traffic and blocking the parking lot for employees
• The unit was fully installed and operational by 10am the same day so they did not go without heat
• We have replaced several units on this building and maintain the service agreement

“Thank you! We had no disruption to our operations today”
– Flynn Commercial Management

Photos of 10 ton rooftop unit in Philadelphia

We are happy to have helped yet another commercial property improve their HVAC system. With these new installations, we know we can guarantee our workmanship for a lifetime. If you need in-ceiling air handler and water coil replacement or have questions about our other services, contact us today for quotes and estimates.

South Jersey CML in Bellmawr, NJ

South-Jersey-CML-Bellmawr-NJ

South Jersey CML in Bellmawr, NJ is the Dunkin Donuts baking and distribution facility in South Jersey. Their location in Bellmawr is crucial to operations, as it is responsible for the on-time, on-budget of bakery supplied goods to its many member franchisees throughout South Jersey. A.M. Botte was tasked with the design and installation of: HVAC Uints, Exhaust Systems and Three New Cook Lines.

We have provided the best HVAC services to several industries in our 20 years of business. We can help you save time and money on your building project by being the sole contractor for your mechanical systems. We are able to keep costs under control by helping you avoid redesigns and multiple bids. After we are finished, we keep continuous communication between the client and our construction contractors.

We installed four new rooftop units with new ductwork for each one. In the kitchen, we put in three Stainless Steel Captiveaire Kitchen Hoods, and Stainless Steel Exhaust Ductwork. By the time the project was finished, we had put three new cook lines into service. 

Services Provides to South Jersey CML in Bellmawr, NJ

  • Installation of  FOUR New 15 Ton York Rooftop Units
  • All New Custom Ductwork for the Four Units
  • Installation of THREE new 40’ Stainless Steel Captiveaire Kitchen Hoods
  • Installation of 20” Stainless Steel Exhaust Ductwork
  • Installation of SIX, 3000 CFM Exhaust Fans
  • Installation of SIX Captiveaire Make Up Air Units
  • Put THREE New Cook Lines Into Service

Photos of South Jersey CML Project in Bellmawr, NJ

 

 

Health Advocate – Plymouth Meeting, PA

Health Advocate Plymouth Meeting PA (4)

Health Advocate in Plymouth Meeting, PA hired AM Botte Commercial HVAC to provide replacement of their heat pump HVAC system as well as new ductwork and air intakes. Health advocate could not close their business operations as they are staffed 7 days per week. AM Botte was able to perform all work at their Plymouth Meeting location during the hours of 6PM – 6AM, causing no interruption to their business operations. We replaced 6 heat pumps, installed 4 fresh air intake systems, all new ductwork with motorized dampers and wired the systems into their building automation control system. 

Highlights of Health Advocate in Plymouth Meeting, PA

  • Upgrade of 6 heat pump split systems
  • Replace 6 systems with new York heat pumps
  • Run all new power wiring and controls for new equipment
  • Run all new refrigerant lines through the existing building
  • Integrated the new units into the building management system
  • Install 4 new fresh air intake fans with all ductwork, motorized dampers and controls
  • All work was done 6pm to 6am after hours ensuring the medical space was un interrupted and clean each do so they were not disrupted
  • All work done in an occupied finished space above ceilings    

Photos of Health Advocate in Plymouth Meeting, PA

TLC Daycare – Voorhees NJ

TLC Daycare in Voorhees, NJ recently hired AM Botte Commercial HVAC division to replace their entire 10 Ton AC system and 300,000 BTU gas furnace. The problem TLC Daycare in Voorhees has was that they couldn’t close down their business while the repairs were being made. AM Botte managed to replace the entire ceiling-based, AC and Furnace system as well as run new ductwork in less than 48 hours from start to finish. Our teams worked around the clock to have TLC Daycare up and running by Monday morning.

Highlights of TLC Daycare in Voorhees, NJ   

  • Replacement of a 10 ton air handler AC system
  • Replacement of 300,000 btu induct gas furnace
  • All work was above a ceiling in the attic
  • Installed 2 York high efficient gas furnaces
  • Installed 2 York 5 ton AC units
  • Made new custom ductwork
  • Did all work over a weekend working around the clock

Photos of TLC Daycare in Voorhees, NJ 

Waynesboro PA Post Office

Waynesboro PA Post Office

A.M. Botte performed a total upgrade of the Waynesboro, PA Post Office HVAC systems. We removed two old rooftop units and replaced them with new York high efficient units. We replaced the old boiler system with a new Burnham boiler and power flame gas burner, offering high and low fire for energy efficiency. We upgraded all the boiler pumps with VFD drives to help with efficiency. Once all the units were replaced,  we upgraded the HVAC controls for the entire building with a modern, building automation system (BAS). This allowed us to connect all the equipment to one central front end and monitor the building operation for maximum efficiency.

The Waynesboro Post Office now has a fully modernized system that will realize annualized savings of thousands of dollars.

Photos of Waynesboro PA Post Office Job

 

Abundant Life Church – Freehold, NJ

Abundant Life Church of God in Freehold, NJ recently added a new Christian Education wing to their church. The church contracted A.M. Botte to handle the design and installation of all the new ducts, HVAC units and building automation controls. The facility now meets the needs of this growing congregation in Freehold, NJ. 

Project Details for Abundant Life Church – Freehold, NJ

  • Ductwork for Kitchen, Foyer, Restrooms and Classrooms
  • Spiral Duct System for Multi-Purpose Room
  • High Efficiency HVAC Units
  • Multi-Zone Building Automation Controls

Photos of Abundant Life Church – Freehold, NJ

Time Lapse Video of Duct Installation

Retro Fitness Center – Glassboro NJ

Retro Fitness Glassboro New Jersey HVAC

Retro Fitness Center in Glassboro, New Jersey had an HVAC system that was over 30 years old. This old 10 Ton HVAC system was wasting energy and barely functioning. AM Botte was tasked with replacing the old units with a modern, Trane system that will save energy and create a more comfortable environment for the members at Retro Fitness in Glassboro. The challenge with this project, was replacing the old roof units without voiding the warranty on the much newer roof. AM Botte was able to  install custom metal adapter curbs to connect to the existing roof curbs eliminating the need to disturb the roof and void the warranty. The two 10 Ton units were seamlessly installed over the new curbs and the work was completed to the customer’s satisfaction.    

Retro Fitness is great BUT Retro HVAC systems waste energy. 

HVAC Replacement Retro Fitness Center – Glassboro NJ