About: vlm

Profile

Author Archives: vlm


Air Handler & Water Coil Replacement In Camden, NJ

Air Handler & Water Coil Replacement In Camden, NJ

We at A.M. Botte were contacted by a new client to do a project involving an Air Handler & Water Coil Replacement in Camden, NJ! The client, Leap Academy contacted us because their old air conditioning system wasn’t running properly and causing the teachers and faculty a ton of problems. All of our work was done on off hours to prevent interruption to the school starting Friday 5pm and finishing on a Sunday afternoon. We removed and installed 4 split air handlers with hot water coils above ceilings throughout the school. The AC units were split between the roof and the ground. The units were in very difficult locations that required us to remove piping, wiring, sprinkler piping and other obstacles. We removed and reinstalled the drop ceilings and cleaned the hallways including mopping the floors, we made all custom ductwork fittings on site with our duct fabrication truck to minimize the down time.

Highlights of Air Handler & Water Coil Replacement In Camden, NJ

  • In ceiling air handler and water coil replacement
  • Installed 4 Split Air Handlers with Water Coils
  • Installed Custom Duct Work
  • Removed Old Air Handlers

“You guys are the best! We can always count on you to get the job done!”
~Raul, Schools Handyman

Photos of job


Have An Issue With Your AC Unit or Want An Upgrade?

Contact Us!

Unit Overhaul In Swedesboro, NJ

Unit Overhaul In Swedesboro, NJ

A.M. Botte recently did a unit overhaul in Swedesboro, NJ! Our new clients of Burton Real Estate contacted us to do an overhaul on their AC & heating units, their old rotting systems weren’t doing the job right anymore so, they reached out to the experts at A.M. Botte! Once we made initial contact we at A.M. Botte sent out a technician to inspect their current AC & heating system, when we determined that this client did in fact need a full overhaul on their current unit we started the process of replacing it. An A.M. Botte installation team was sent out as soon as it was available, our install team was able to get the old system removed and the new unit installed in a timely and respectful manner. Burton Real Estate was very happy with the work that the experts at A.M. Botte did, their new unit properly heats & cools the building to the optimal temperatures making sure that their company can function and work comfortably!

Highlights of the Unit Overhaul In Swedesboro, NJ:

  • 80,000 square foot Building overhaul
  • We hung and installed 17-350,000 btu hanging unit heaters 32” in the air
  • We ran all the flue piping through the roof for each hanging unit
  • We ran 2500’ of welded and threaded gas piping ranging from ½’ to 3”
  • We replaced 6 roof top package units for the office areas
  • Excavated and Repaired 22 floor drains
  • We fabricated a custom 6’ diameter steel ejector pit cover
  • We install 2 new 3hp ejector pit pumps with a new field fabricated mounting system and all new piping and check valves
  • We repaired the roof access ladder and safety cage

Photos of Job:


Have An Issue With Your AC Unit or Want An Upgrade?

Contact Us!

10 Ton RTU Replacement In Philadelphia, PA

10 Ton RTU Replacement In Philadelphia, PA

A.M. Botte recently did a 10 ton RTU replacement in Philadelphia, PA. The Client Flynn Commercial Property Management was having trouble with their heating & cooling unit that we installed over 15 years ago, the old system was malfunctioning and causing the employees to feel cold or hot depending on the outside weather. This winter they finally had enough and called the experts at A.M. Botte, we sent out a technician to take a look at their machine and give them an estimate. Our technician saw that the machine was a dinosaur and needed to be replaced, and the business owners agreed. Once everything was set an installation team was sent out to do the 10 ton RTU replacement in Philadelphia, PA. Our team went out at 5 AM to avoid inconveniencing the employees of Flynn Commercial Property Management. Once everything was completed the client was ecstatic to finally have a properly conditioned office!

Company Name of Customer: Flynn Commercial Property Management

Address of Service: Philadelphia PA

Highlights of 10 Ton RTU Replacement In Philadelphia, PA

10 ton RTU replacement for office area
The unit that we installed over 15 years ago was due for replacement
The work was scheduled at 5am start to avoid traffic and blocking the parking lot for employees
The unit was fully installed and operational by 10am the same day so they did not go without heat
We have replaced several units on this building and maintain the service agreement

Photos of job: 


Have An Issue With Your AC Unit or Want An Upgrade?

Contact Us!

Boiler Installation In Cape May, NJ

Boiler Installation In Cape May, NJ

A.M. Botte recently did a boiler installation in Cape May, NJ. We were proud to serve our new client, The United States Coast Guard. They were in need of a new boiler system and after careful consideration they contacted the experts at A.M. Botte. The U.S. Coast Guard informed us that their old outdated boiler which resided in a small pantry closet in their mess hall kitchen was not functioning properly and needed to be replaced. After they informed us of this we got right to work, and sent out a team to remove the old boiler system. After this was done our technicians installed a brand new Combi boiler system, this new boiler system allows hot water to be endlessly used to the homeowner, or in this case The United States Coast Guard! The United States Coast Guard was satisfied to say the least, their new boiler system was installed in a timely fashion, and the whole job was completed at the agreed upon time!

Highlights of Boiler Installation In Cape May, NJ:

  • Removed old, outdated boiler and water heater from small pantry closet in kitchen. Provided more storage space in kitchen closet
  • Installed new Cascading Lochinvar Combi Boiler System
  • Combi boiler allows for endless hot water to the homeowner
  • Efficiency of new system will allow for lower energy bills for years to come

“The team went above and beyond. All of our questions were answered and the job was completed in the agreed upon timeline.”  -United States Coast Guard

Photos of  Job


Have An Issue With Your AC Unit or Want An Upgrade?

Contact Us!

New Rooftop Package at Independent Record Pressing

New Rooftop Package at Independent Record Pressing

A.M. Botte was contracted for an entire HVAC design build project at Independent Record Pressing in Bordentown, New Jersey. We provided a total turnkey mechanical job for our customer. The project included (8) 12.5 ton York rooftop package units. A.M. Botte performed all structural steel work for the new equipment, including roof openings and roof flashing. On the inside of the building we installed all new exposed spiral duct work with enlarged diffusers. On the outside of the building we installed a new, 200 ton, York air cold water chiller on a new 6 inch concrete housekeeping pad. We fabricated all new 6 inch welded steel pipe for the new chiller with custom pump assemblies. Our team also included all needed line voltage power to complete this project. The facilities manager Sal was very pleased with all the work performed and has since awarded A.M. Botte the maintenance agreement on for the entire building.

Emergency HVAC Replacement for Woodcrest Country Club

Emergency HVAC Replacement for Woodcrest Country Club

We were called to an emergency service (outage) call at Woodcrest Country Club, where we found that two of the main package HVAC units had failed. Due to the severity of the call, we sent our General Manager and Service Manager to make emergency repairs and keep the units running while a replacement could be designed. Our team was able to order, and build to custom specifications, two new 30 ton and 40 ton York gas electric package units. These units took approximately 16 weeks to be built, so we tasked our service department with keeping the old units running the best they could during this busy time for Woodcrest Country Club. Once the new units arrived, we executed our detailed plan for their replacement. We worked to schedule around multiple events our client had, and selected a strategic day for the work to be completed. Utilizing a 125 ton Crane, and a large group of manpower, we were able to complete this replacement in one day with no disruption to the customer.

WATCH – Emergency HVAC Replacement for Woodcrest Country Club

HVAC Package for Tonewood Brewery in Barrington, NJ

HVAC Package for Tonewood Brewery in Barrington, NJ

A.M. Botte recently completed an entire HVAC system installation at Tonewood Brewery in Barrington, NJ. We were hired by Eli Facchinei, who is the owner/operator to design build and install all new HVAC for his new  brewery location in Barrington, NJ. We installed (2) York 15 ton RTU’s with exposed duct work on the roof. The duct work then dropped down and transitioned into double wall custom oval/round spiral. We installed (2) Macroaire 10’ diameter fans along with (1) 14’ diameter fan, these units where installed over top of the vats to assist in cooling the space. We installed (4) high efficiency Reznor unit heaters in the brewing area. We also installed a York mini split to provide heating and cooling in the lab. With craftsmanship and attention to detail our team was able to design build and install all of the HVAC on time and in budget. Craftsmanship that will last a lifetime! 

Highlights of HVAC Package for Tonewood Brewery in Barrington, NJ

  • Complete System and Ductwork Design
  • 2 York 15 Ton Units
  • 2 Macroaire 10’ diameter fans
  • 1 14’ diameter fan
  • 4 high efficiency Reznor heaters
  • 1 York mini split system

“The oval duct was a great idea we love it!”
– Eli Facchinei: Owner, Tonewood Brewery

Photos of HVAC Package for Tonewood Brewery in Barrington, NJ

10 Ton Rooftop Unit in Philadelphia for Flynn Property Management

10 Ton Rooftop Unit in Philadelphia for Flynn Property Management

We recently installed a 10 ton rooftop unit in Philadelphia for Flynn Commercial Property Management. Our team got into and out of Philadelphia before the traffic rush and got this valued commercial customer up and running without downtime. Anytime we are called to do work in the city, we make sure our cranes are on-site well ahead of the morning traffic rush and out of the city before noon. This customer saw absolutely no disruption to their daily routine and our installation likely went unnoticed by their tenants.  

Highlights of this 10 ton rooftop unit in Philadelphia

• The unit that we installed over 15 years ago was due for replacement
• The work was scheduled at 5am start to avoid traffic and blocking the parking lot for employees
• The unit was fully installed and operational by 10am the same day so they did not go without heat
• We have replaced several units on this building and maintain the service agreement

“Thank you! We had no disruption to our operations today”
– Flynn Commercial Management

Photos of 10 ton rooftop unit in Philadelphia

We are happy to have helped yet another commercial property improve their HVAC system. With these new installations, we know we can guarantee our workmanship for a lifetime. If you need in-ceiling air handler and water coil replacement or have questions about our other services, contact us today for quotes and estimates.

South Jersey CML in Bellmawr, NJ

South-Jersey-CML-Bellmawr-NJ

South Jersey CML in Bellmawr, NJ is the Dunkin Donuts baking and distribution facility in South Jersey. Their location in Bellmawr is crucial to operations, as it is responsible for the on-time, on-budget of bakery supplied goods to its many member franchisees throughout South Jersey. A.M. Botte was tasked with the design and installation of: HVAC Uints, Exhaust Systems and Three New Cook Lines.

We have provided the best HVAC services to several industries in our 20 years of business. We can help you save time and money on your building project by being the sole contractor for your mechanical systems. We are able to keep costs under control by helping you avoid redesigns and multiple bids. After we are finished, we keep continuous communication between the client and our construction contractors.

We installed four new rooftop units with new ductwork for each one. In the kitchen, we put in three Stainless Steel Captiveaire Kitchen Hoods, and Stainless Steel Exhaust Ductwork. By the time the project was finished, we had put three new cook lines into service. 

Services Provides to South Jersey CML in Bellmawr, NJ

  • Installation of  FOUR New 15 Ton York Rooftop Units
  • All New Custom Ductwork for the Four Units
  • Installation of THREE new 40’ Stainless Steel Captiveaire Kitchen Hoods
  • Installation of 20” Stainless Steel Exhaust Ductwork
  • Installation of SIX, 3000 CFM Exhaust Fans
  • Installation of SIX Captiveaire Make Up Air Units
  • Put THREE New Cook Lines Into Service

Photos of South Jersey CML Project in Bellmawr, NJ

 

 

Health Advocate – Plymouth Meeting, PA

Health Advocate Plymouth Meeting PA (4)

Health Advocate in Plymouth Meeting, PA hired AM Botte Commercial HVAC to provide replacement of their heat pump HVAC system as well as new ductwork and air intakes. Health advocate could not close their business operations as they are staffed 7 days per week. AM Botte was able to perform all work at their Plymouth Meeting location during the hours of 6PM – 6AM, causing no interruption to their business operations. We replaced 6 heat pumps, installed 4 fresh air intake systems, all new ductwork with motorized dampers and wired the systems into their building automation control system. 

Highlights of Health Advocate in Plymouth Meeting, PA

  • Upgrade of 6 heat pump split systems
  • Replace 6 systems with new York heat pumps
  • Run all new power wiring and controls for new equipment
  • Run all new refrigerant lines through the existing building
  • Integrated the new units into the building management system
  • Install 4 new fresh air intake fans with all ductwork, motorized dampers and controls
  • All work was done 6pm to 6am after hours ensuring the medical space was un interrupted and clean each do so they were not disrupted
  • All work done in an occupied finished space above ceilings    

Photos of Health Advocate in Plymouth Meeting, PA